BIKINNOV - Bike Value Innovation Center - Association
Automated case report generated from contract-level risk evidence.
Executive Highlights
3 companies receive 38.5% of total spend
69 of 133 contracts (51.9%) have active risk signals
Supplier concentration is low (HHI 0.0793)
10 individuals (aggregate count) linked to 1 winner companies
Person-company link evidence is available for 1 of 66 winner companies (1.5%); 65 have no link data
Award timing distribution is within expected bounds: 32.3% in Mar/Jun/Sep/Dec; 10.5% in December
Key Metrics
| Company | Awarded value | Share |
|---|---|---|
| IZASA Scienyific, Unipessoal, Lda. | €5,919,500 | 22.5% |
| NM3D Ibérica - Sistemas de Metrologia Industrial, Lda. | €2,215,000 | 8.4% |
| DEIBAR - Máquinas Ferramenta, Lda | €1,965,000 | 7.5% |
Network Cluster Map
Main cluster focused on this entity with person-company links.
Whole Procurement Map
Global contract links across public bodies and companies
Public mode hides individual nodes and shows only connected-individual totals.
Navigate: drag to pan, use mouse wheel to zoom, and reset view when needed.
Top 30 High-Risk Contracts
Highest combined risk score, with indicator evidence.
| Contract | Date | Value | Risk | Evidence |
|---|---|---|---|---|
|
Eixo Materiais Tomografia Computadorizada
10953125
|
2024-09-06 | €2,049,500 | 115 (3) |
B5 · Benford's Law Deviation
(55)
chi2=23.6594 | sample_size=132
A2 · Late Publication
(40)
publication_date=2024-10-04 | celebration_date=2024-09-06
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Contratação de Especialista em ligas leves para Trabalho de I&D no Setor das Duas Rodas
11424226
|
2025-05-07 | €72,000 | 60 (2) |
A5 · Threshold Splitting
(35)
base_price=74000.0 | threshold=75000.0
C1 · Missing Supplier NIF
(25)
rule=C1 no winner recorded: awarded contract (effective price > 0) has no supplier identified
|
|
Alteração de Revestimento de Fachadas
10974916
|
2024-08-26 | €44,289 | 60 (2) |
A2 · Late Publication
(40)
publication_date=2024-10-16 | celebration_date=2024-08-26
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Obras de beneficiação das instalações AEA para nova funcionalidade do edifício
10891129
|
2024-02-07 | €168,559 | 60 (2) |
A2 · Late Publication
(40)
publication_date=2024-08-28 | celebration_date=2024-02-07
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Prestação de Serviços de Auditoria de 2024 a 2026
10786953
|
2024-06-20 | €10,800 | 55 (2) |
A5 · Threshold Splitting
(35)
base_price=19000.0 | threshold=20000.0
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Aquisição de Solução de Comunicações Integrada para o Centro de Tecnologia e Inovação
11170888
|
2025-01-06 | €9,435 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2025-01-17 | celebration_date=2025-01-06
A9 · Abnormal Price Reduction
(10)
base_price=22000.0 | total_effective_price=9435.0
|
|
Eixo Materiais Caracterização Mecânica e à Fadiga de Materiais
11009193
|
2024-09-26 | €149,364 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2024-11-05 | celebration_date=2024-09-26
A9 · Abnormal Price Reduction
(10)
base_price=675000.0 | total_effective_price=149364.0
|
|
Eixo Materiais Caracterização de Propriedades
10788337
|
2024-05-24 | €29,481 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2024-06-25 | celebration_date=2024-05-24
A9 · Abnormal Price Reduction
(10)
base_price=290000.0 | total_effective_price=29481.0
|
|
Eixo Materiais Caracterização de Propriedades
10788333
|
2024-05-24 | €127,900 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2024-06-25 | celebration_date=2024-05-24
A9 · Abnormal Price Reduction
(10)
base_price=290000.0 | total_effective_price=127900.0
|
|
Eixos Tecnologias de Produção / Processos Industriais Prototipagem
10700380
|
2024-04-23 | €117,628 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2024-05-06 | celebration_date=2024-04-23
A9 · Abnormal Price Reduction
(10)
base_price=797500.0 | total_effective_price=117628.0
|
|
Capacitação para Desenvolvimento de Projetos I
9976504
|
2023-04-24 | €87,262 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2023-05-08 | celebration_date=2023-04-24
A9 · Abnormal Price Reduction
(10)
base_price=967270.0 | total_effective_price=87262.0
|
|
Capacitação para Desenvolvimento de Projetos I
9976501
|
2023-04-19 | €400,886 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2023-05-08 | celebration_date=2023-04-19
A9 · Abnormal Price Reduction
(10)
base_price=967270.0 | total_effective_price=400886.0
|
|
Capacitação para Desenvolvimento de Projetos I
9976508
|
2023-04-27 | €45,460 | 50 (2) |
A2 · Late Publication
(40)
publication_date=2023-05-08 | celebration_date=2023-04-27
A9 · Abnormal Price Reduction
(10)
base_price=967270.0 | total_effective_price=45460.0
|
|
Aquisição de Serviços para o Licenciamento de Alterações em Obra e Autorização de Utilização do Centro de Tecnologia e Inovação
11067720
|
2024-12-03 | €12,350 | 45 (2) |
C1 · Missing Supplier NIF
(25)
rule=C1 no winner recorded: awarded contract (effective price > 0) has no supplier identified
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Eixo Desenvolvimento de Produto – Digitalização Bancos de Fadiga
10544848
|
2024-02-06 | €15,000 | 45 (2) |
C1 · Missing Supplier NIF
(25)
rule=C1 no winner recorded: awarded contract (effective price > 0) has no supplier identified
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
|
|
Empreitada de Fornecimento e Instalação de Novo Quadro Geral de Baixa Tensão para o CTI
11741698
|
2025-09-09 | €44,800 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2025-09-24 | celebration_date=2025-09-09
|
|
Empreitada para Pintura do Pavimento Interior do Pavilhão Poente do CTI
11649705
|
2025-06-16 | €45,933 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2025-08-20 | celebration_date=2025-06-16
|
|
Empreitada para Execução de Trabalhos relativos a Sistemas de Segurança Contra Incêndios
11585034
|
2025-04-16 | €40,296 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2025-07-15 | celebration_date=2025-04-16
|
|
Empreitada de Adaptação dos Pavilhões 1, 2 e 3 da AEA, para acolhimento das instalações do Centro de Tecnologia e Inovação
11254445
|
2023-12-19 | €346,231 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2025-02-28 | celebration_date=2023-12-19
|
|
O objeto do presente procedimento consiste na aquisição de uma estação de trabalho portátil que permita uma flexibilidade de trabalho
11116851
|
2024-10-30 | €1,443 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2024-12-30 | celebration_date=2024-10-30
|
|
Empreitada criação de divisões e colocação de teto na área de receção/administrativa do CTI
10961186
|
2024-09-09 | €95,502 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2024-10-09 | celebration_date=2024-09-09
|
|
Sistema de Produção de Ar Comprimido
10929540
|
2024-08-30 | €29,743 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2024-09-20 | celebration_date=2024-08-30
|
|
Aquisição de Pacote de Viagens 2024
10771400
|
2024-05-27 | €41,872 | 40 (1) |
A2 · Late Publication
(40)
publication_date=2024-06-17 | celebration_date=2024-05-27
|
|
Aquisição de Serviços para a Elaboração do Projeto de Execução de Sala de Realidade Imersiva do CTI
11787079
|
2025-10-10 | €74,097 | 35 (1) |
A5 · Threshold Splitting
(35)
base_price=74500.0 | threshold=75000.0
|
|
Definição da estratégia e Suporte à implementação do Plano de Promoção e Divulgação do CTI AM2R Agenda Mobilizadora para a Inovação Empresarial do setor das duas rodas
11392571
|
2025-05-02 | €72,500 | 35 (1) |
A5 · Threshold Splitting
(35)
base_price=74000.0 | threshold=75000.0
|
|
Aquisição de Consultoria para Benchmarking de Inovação e Modelos de Desenvolvimento Industrial no Setor das Duas Rodas
10827081
|
2024-07-11 | €73,000 | 35 (1) |
A5 · Threshold Splitting
(35)
base_price=74000.0 | threshold=75000.0
|
|
Eixo de Desenvolvimento de Produto Prototipagem e Preparação
11192838
|
2025-01-24 | €12,900 | 30 (2) |
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
A9 · Abnormal Price Reduction
(10)
base_price=60000.0 | total_effective_price=12900.0
|
|
Eixo de Desenvolvimento de Produto Prototipagem e Preparação
11192864
|
2025-01-23 | €4,000 | 30 (2) |
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
A9 · Abnormal Price Reduction
(10)
base_price=60000.0 | total_effective_price=4000.0
|
|
Eixo Materiais – Microscopia e Preparação de amostras
10555598
|
2024-02-12 | €97,727 | 30 (2) |
A6 · Low Competition
(20)
rule=a6_single_bidder | bidder_count=1
A9 · Abnormal Price Reduction
(10)
base_price=1800000.0 | total_effective_price=97727.0
|
|
Eixo Desenvolvimento de Produto Sistema de Crash Test para Produtos da Mobilidade Suave
12951453
|
2026-01-27 | €707,500 | 25 (1) |
C1 · Missing Supplier NIF
(25)
rule=C1 no winner recorded: awarded contract (effective price > 0) has no supplier identified
|
Award Timeline
Monthly award volume and amendment risk signals.
| Period | Awards | Awarded value | Amendment signals |
|---|---|---|---|
| 2023-02 | 1 | €12,936 | 0 |
| 2023-04 | 3 | €533,608 | 0 |
| 2023-06 | 2 | €248,248 | 0 |
| 2023-10 | 1 | €51,775 | 0 |
| 2023-12 | 1 | €346,231 | 0 |
| 2024-02 | 4 | €1,979,786 | 0 |
| 2024-04 | 1 | €117,628 | 0 |
| 2024-05 | 6 | €796,133 | 0 |
| 2024-06 | 4 | €193,568 | 0 |
| 2024-07 | 2 | €113,350 | 0 |
| 2024-08 | 4 | €135,049 | 0 |
| 2024-09 | 5 | €2,387,499 | 0 |
| 2024-10 | 3 | €463,043 | 0 |
| 2024-11 | 1 | €8,323 | 0 |
| 2024-12 | 4 | €368,454 | 0 |
| 2025-01 | 12 | €1,231,958 | 0 |
| 2025-02 | 1 | €87,500 | 0 |
| 2025-03 | 6 | €332,644 | 0 |
| 2025-04 | 6 | €395,614 | 0 |
| 2025-05 | 7 | €605,636 | 0 |
| 2025-06 | 4 | €420,080 | 0 |
| 2025-07 | 5 | €234,959 | 0 |
| 2025-08 | 1 | €67,900 | 0 |
| 2025-09 | 8 | €591,556 | 0 |
| 2025-10 | 6 | €1,338,794 | 0 |
| 2025-11 | 10 | €1,055,283 | 0 |
| 2025-12 | 9 | €1,112,782 | 0 |
| 2026-01 | 10 | €1,846,329 | 0 |
| 2026-02 | 6 | €80,770 | 0 |
Risk scoring combines rule-based indicators with data quality flags. Values and confidence degrade when critical fields are missing.